About COWI
Contact COWI
Sitemap
COWI sites
ProjectPortal
Engineering, Environmental Science and Economics
Search
Home
Services
Projects
Publications
Jobs
News
Special features
Nature
Society
Transport
Buildings
Industry
Utilities
Projects
/
Industry
/
Oil and gas
/
Offshore facilities
/
Siri field wellhead module
Environmental and social due diligence
Health, safety and environment
Industrial buildings
Oil and gas
Decommissioning
Offshore facilities
Transmission and distribution
Onshore facilities
Production and processing plants
Industrial project management
Industrial planning and logistics
Production and processing plants
Industrial IT and automation
Industrial production management
Industrial utilities
Siri field wellhead module
The SIRI Field is an oil field in the northern part of the Danish North Sea.
The SIRI platform concept represents a revolutionary new way of thinking both as regards total installation cost for a relatively marginal field and the record breaking time schedule with drilling start within 15 months and first oil within 21 months after EPCI contract award.
The concept consists of a 10,000 t production jack-up platform standing on a 50,000 m
3
sub sea storage tank. Part of the topside facilities includes the 450 t wellhead area designed by COWI for Kværner Oil and Gas AS.
The wellhead area is designed for 12 wells totally with 6 producers and 3 injectors planned initially. Manifolds are installed for production, test, gas lift/re-injection and water injection. Furthermore, the area also includes all interfaces between the production jack-up and the storage tank and off-loading.
The Xmas tree area is made as a minimum deck facility mounted on the 5.25 m outside diameter wellhead caisson pre-installed in the storage tank. This enables pre-drilling and completion of wells 6 months prior to topside installation.
The remaining part of the wellhead area including manifolds and pipe rack is installed on a separate jackable structure on the production jack-up for offshore hook-up to wells.
This part is elevated 8 m during sea transportation of the production jack-up to clear the waves.
Want to know more?
Johnny Mikkelsen
Head of Department, Oil and Gas
Tel.: +45 45 97 27 49
jmi@cowi.dk
Lars Hansen
Chief Project Manager, Oil and Gas
Tel.: +45 79 18 17 80
lahs@cowi.dk
Facts about the project
Project duration:
1997-1998
Client:
Kværner Oil and Gas AS Norway
Specialist services:
Conceptual design assistance, detailed design: Wellhead caisson mechanical outfitting; topside wellhead area; flare tower, safety analysis
Platform key data:
Water depth: 65 m
Jack-up weight: 10,000 t
Storage capacity: 50,000 m3
Wellslots: 12