About COWI
Contact COWI
Sitemap
COWI sites
ProjectPortal
Engineering, Environmental Science and Economics
Search
Home
Services
Projects
Publications
Jobs
News
Special features
Nature
Society
Transport
Buildings
Industry
Utilities
Projects
/
Industry
/
Production and processing plants
/
Industrial project management
/
New slaughterhouse in Horsens, Denmark
Environmental and social due diligence
Health, safety and environment
Industrial buildings
Oil and gas
Decommissioning
Offshore facilities
Transmission and distribution
Onshore facilities
Production and processing plants
Industrial project management
Industrial planning and logistics
Production and processing plants
Industrial IT and automation
Industrial production management
Industrial utilities
New slaughterhouse in Horsens, Denmark
Having analysed the production processes in the pig slaughterhouse field, Danish Crown, owning the largest slaughterhouses in Europe, decided to build the world’s most energy-conscious and environmentally sound slaughterhouse.
The new facilities should supply competitive fresh pork products which fulfil the requirements of the customers as to quality, production guarantee and variety.
The slaughterhouse was constructed according to known technology, hereby ensuring that the resources were used in the best possible way and at the same time taking due consideration to both working environment and surroundings.
As the main consultant, COWI designed all engineering and architectural works with the assistance of 4 specialist consulting companies in the design of the process plant.
The total investment costs provided for in the budget amount to 300 mio. USD. This made the project the largest private industrial project ever constructed in one stage in Denmark.
The slaughterhouse has a weekly capacity of 75,000 pigs to be processed by 1,400 workers. The buildings cover an area of 76,000 m
2
.
The facilities comprise slaughter lines, cooling tunnels and cold stores, cutting and boning lines and wrapping and dispatch rooms. At a later stage, freezing facilities in the immediate vicinity of the plant will be established.
The design started in January 2001, start of construction took place in August 2002 and commissioning took place in September 2004.
Want to know more?
Jan Stockmarr
Chief Project Manager, Industry
Tel.: +45 76 42 65 00
jst@cowi.dk
Facts about the project
Project period:
2001-2004
Client:
Danish Crown a.m.b.a
Services rendered by COWI:
Project management, master planning, buildings, utilities, logistics, energy-conscious planning, environmental aspects (HSE), IT-systems, site supervision, project follow-up, commissioning