The Abu Dhabi Strategic Tunnel Enhancement Programme provides a major improvement in the capacity of Abu Dhabi’s waste water system.
The project includes a new deep gravity sewer tunnel which takes the main sewer flows from Abu Dhabi to a new treatment works outside the city, and a series of link sewers connecting into the deep tunnel.
The new deep gravity sewer tunnel is 45km in length. It varies in diameter from 5 to 6-8 metres along its length.
The tunnel was constructed with seven earth pressure balance (EPB) tunnel boring machines (TBMs) which were launched and operated from seven deep shafts.
LOCATION:
Abu Dhabi, UAE
PERIOD:
2009-2013
CLIENT:
Impregilo S.p.A
COWI'S SERVICES:
Vincenzo Zeuli
Chief Specialist
Tunnels and Underground Infrastructure, Denmark
Tel:
+45 56407846
vize@cowi.com